These are some of the top projects in this category covered in New Projects Tracker portal in October 2023.

 

Project Promoter : Globus Spirits Ltd

Products & Capacity : Grain Based Distillery (300 KLPD), Malt Spirit (15 KLPD)

Project Location : Abbaspur, Mitauli, Kheri, Uttar Pradesh

Proposed Investment : 2500 ( Rs. Million )

Project Completion : March 2025

Executive Summary : Globus Spirits Ltd is undertaking a pioneering grain-based distillery manufacturing project in Kheri, Uttar Pradesh. The comprehensive initiative encompasses a proposed distillery, malt spirit plant, and co-generation power plant, with an estimated cost of Rs. 2500 million. Construction is scheduled to commence in September 2023 and conclude in March 2025. As of October 2023, the project has been submitted to the Ministry of Environment, Forest, and Climate Change in India.

 

Project Promoter : Taru Formalin Pvt Ltd

Products & Capacity : Formaldehyde (300 MT/Day)

Project Location : GIDA, Sahjanwa, Gorakhpur, Uttar Pradesh

Proposed Investment : 90 ( Rs. Million )

Project Completion : Dec 2024

Executive Summary : Taru Formalin Pvt Ltd is actively progressing with a formaldehyde manufacturing project in GIDA, Sahjanwa, Gorakhpur, Uttar Pradesh, as of October 2023. Geared to produce 300 metric tons daily, the project carries an estimated cost of Rs. 90 million, with construction scheduled from June 2026 to December 2024. Emphasizing responsible industrial development, the project's environmental impact assessment has been submitted for clearance, showcasing a commitment to environmentally sustainable practices.

 

Project Promoter : Ghaziabad Organics Ltd

Products & Capacity : Distillery (50 KLD)

Project Location : Bhojpur, Modinagar, Ghaziabad, Uttar Pradesh

Proposed Investment : 434.5 ( Rs. Million )

Project Completion : April 2025

Executive Summary : Ghaziabad Organics Ltd, a distillery company in Uttar Pradesh, is set to enhance its manufacturing capacity. The expansion project focuses on elevating ethanol production from 50 KLD to 115 KLD, primarily utilizing grains. With an estimated cost of Rs. 434.5 million, construction is slated to commence in December 2023, concluding in April 2025. The project has been formally submitted to the Ministry of Environment, Forest, and Climate Change in India, and as of October 2023, the environmental clearance process is currently under examination.

 